S | M | T | W | T | F | S |
---|---|---|---|---|---|---|
|
|
|
|
|
1 |
2 |
3 |
4 |
5 |
|
7 |
8
|
9
|
10 |
|
|
|
|
15 |
16
|
17 |
|
|
|
21
|
22 |
23 |
24 |
|
26
|
|
|
29
|
30 |
Upcoming Events
September 26, 2023 - 8:00am to 4:00pm
September 26, 2023 - 6:00pm
September 27, 2023 - 8:00am to 5:00pm
September 27, 2023 - 4:00pm
September 28, 2023 - 8:00am to 4:00pm
Polling Location Change »
IMPORTANT NOTICE
to Adams Registered VotersPolling Location ChangeEffective immediately (April 7...
65 Park Street Entrance Improvement Project
Scope:
- Installation of a stair lift to achieve compliance with the Americans with Disabilities Act.
Contractor:
- Salco Construction
Notice to Public:
- The entrance to the building, which serves as the Northern Berkshire Registry of Deeds is currently closed. Patrons can call the number posted on the outside of the building for services.
Schedule:
- Planned completion in the middle of September, 2021
1 Cook Street Hazardous Material Remediation
Scope:
- Removal of hazardous material inside the former grain elevator building at 1 Cook Street, including asbestos, lead abatement and garbage removal.
Contractor:
- Gem Environmental
Notice to Public:
- None
Schedule:
- Planned completion by September 3, 2021
Commercial Street/Route 8 Improvement Project
Scope:
- Full-depth road repaving, sidewalks, drainage and sewage line upgrade
Contractor:
- Maxymillion/ MassDOT Project Manager
Notice to Public:
- Weeks 8/12 through 9/6 new curbs and temporary traffic lines and crosswalks will be installed in the northern 2/3 section of the route, approximately from Elm Street north to Center Street. The remaining southerly third of the project will undergo full depth excavation starting after Labor Day with a plan to pave the section in early October.
Schedule:
- Completion in 2022